SCA:s new grading mill is taking shape

Photo: Fredrik Molin

Right now, the base of SCA’s new grading mill i being built. At the same time, preparations are being made for piling and other tasks to be able to complete the rest of the building.

The building where the new grading mill will be housed will be approximately 200 meters long. The work is going according to plan and in September 2021 the building will be ready for installation of machine equipment. The new grading mill will be put into operation in the autumn of 2022.

The building for the new workshop has been completed and is currently being put into use. In the building there is space for both offices and a new storage room. The total area is 1950 m2.